Washway Road . Sale
- Gross Development Value: £3.5 million
- Site Acquisition: December 2003
- Funding: December 2003
- Planning: August 2003
- Pre-letting: October 2006
- Development Funding: Cheshire Building Society
- Construction: Due to complete November 2006
- Contract: JCT 98 Design and Build
- Contract Price: £1.5 million
- Contract Period: 52 weeks
- Contractor: Bardsleys