Quadrangle Manchester

  • Gross Development: In excess of £50 million
  • Site Acquisition: March 2000
  • Funding: March 2000
  • Planning: August 2002
  • Pre-letting: April 2004
  • Construction: Completed Feb 2006
  • Contract: JCT 98 Design and Build
  • Contract Price: £26.5m
  • Contract Period: 125 weeks
  • Contractor: Carillion